West Virginia mechanics lien and payment rules

As a subcontractor in West Virginia, you have 100 days after your last day furnishing labor or materials to record a mechanics lien. Here are West Virginia's notice, lien, bond claim, retainage and prompt payment rules in plain language, with the statutes and a worked example.

  • Reviewed
  • 3 statutes cited
  • Not legal advice

West Virginia at a glance

Private commercial work, sub hired by the GC, unless noted
Preliminary notice (subs)
No general preliminary notice
Record the lien (subs)
100 days after your last day furnishing labor or materials Verify GCs: 90 days after your last day furnishing labor or materials.
Sue to enforce
6 months after recording the lien
Public retainage cap
Verify with state statute
Private retainage cap
Verify with state statute
GC pays subs within
Verify with state statute

Turn these rules into dates for your job, free in your browser.

Preliminary notices in West Virginia

West Virginia is one of the states with no general preliminary notice for subcontractors on commercial work in our summary. That doesn't mean you can skip paperwork: the lien itself still has a hard deadline, and the owner often learns about your claim only when the lien is recorded.

Lien filing deadline in West Virginia

If the GC hired you, you have 100 days after your last day furnishing labor or materials to record a mechanics lien in West Virginia, about 10 days longer than the national median of 90 days (counted from last furnishing on a sample job). 29 of the 51 jurisdictions we track have a shorter lien deadline and 21 have a longer one.

We mark this deadline "verify": the statute has variations we could not reduce to one number.

The clock starts on your last day furnishing labor or materials under your contract. In many states, warranty visits and punch list work done mainly to extend the deadline don't restart it, so use your last day of real contract work.

If you're the GC, in contract with the owner, you have 90 days after your last day furnishing labor or materials instead.

Deadline to sue on the lien

To keep the lien alive you must sue to enforce it within 6 months after recording the lien. If you record on the last possible day, that is about 281 days after your last day on the job, about 84 days shorter than the national median of 365 days. 16 of the 48 jurisdictions we track have a shorter overall time to sue and 31 have a longer one.

Because the clock counts from recording, recording early also moves the lawsuit deadline earlier.

How West Virginia compares

Days are counted on a sample job with the lien recorded on its last allowed day, so states that count from recording or from completion can be compared with those that count from your last day on site. The median is across the jurisdictions with a dated rule on file.

West Virginia deadlines vs the national median
Record the lien (from last day)
West Virginia: 100 days
National median: 90 days
Sue to enforce (from last day)
West Virginia: 281 days
National median: 365 days

Public and federal projects

Public property can't be liened, so subcontractors and suppliers on state and local public jobs in West Virginia claim against the GC's payment bond instead. We haven't reduced West Virginia's bond claim deadlines to one set of numbers, because they vary by agency and project. The governing law is W. Va. Code §38-2-39. Verify the notice and suit deadlines with the statute and the bond itself before the job starts.

Federal jobs in West Virginia follow the Miller Act instead of state law: those hired by a sub or supplier give the prime contractor notice within 90 days of their last furnishing, and suit is due within 1 year, in federal court. Prime contractors on federal work have no lien or bond claim.

Retainage and prompt payment in West Virginia

We haven't reduced West Virginia's retainage and prompt payment rules to single numbers yet: they depend on the agency, the contract size or the contract date. Rather than guess, the table shows "Verify" and the statutes to read are W. Va. Code §5-22 (public). Your contract's payment terms still matter, and the federal rules below apply on federal work.

Retainage and prompt payment in West Virginia
Public workPrivate workFederal work
Retainage capVerifyVerify10%
ReleaseVerify with state statuteVerify with state statuteReleased with final payment, or earlier once progress is satisfactory.
GC pays subs withinVerifyVerify7 days
Late-payment interestVerifyVerifyTreasury prompt payment rate (reset every January and July)

Not legal advice. Retainage and prompt payment rules differ by agency, contract size and contract date, and change often. Confirm the rules with the current statute, your contract and a construction attorney before relying on them.

Worked example: a HVAC sub in West Virginia

A HVAC subcontractor hired by the GC on a private apartment building in West Virginia starts work on March 2, 2026 and last furnishes on July 17, 2026. The project is completed on August 28, 2026. Run through West Virginia's rules, those dates give:

Deadlines for the worked example in West Virginia
DeadlineDateCounted from
Record the lien October 25, 2026 WeekendVerify Last furnishing
Sue to enforce the lien April 25, 2027 Weekend Lien recording

The first deadline on the calendar is “Record the lien” on October 25, 2026.

2 dates land on a weekend (October 25, 2026, April 25, 2027). Not every state rolls a deadline to Monday, so the safe move is to record or serve by the Friday before.

Rows marked "Verify" depend on facts or readings we can't settle for you. Check them against W. Va. Code §38-2-1 to -39.

Open the lien deadline calculator for West Virginia and enter your own dates to get this table for your job, with countdowns and a PDF deadline calendar.

Check your own dates with the free tools

Statutes cited

  • W. Va. Code §38-2-1 to -39
  • W. Va. Code §38-2-39 (public bonds)
  • W. Va. Code §5-22 (public)
  • Federal work in West Virginia: 40 U.S.C. §3131 to §3134 (Miller Act)

Not legal advice. Lien and bond claim rules change and have exceptions for project type, contract terms and how notices are served. Confirm every deadline with the current statute or a construction attorney in the project's state before relying on it. Rules shown as "Verify with state statute" have exceptions or variations we could not reduce to one number.

West Virginia lien and payment FAQs

How long do I have to file a mechanics lien in West Virginia?

If you're a subcontractor or supplier hired by the GC, you have 100 days after your last day furnishing labor or materials. A GC in contract with the owner has 90 days after its last day furnishing labor or materials. Check the exact date for your job with the free lien deadline calculator, and confirm it with the statute (W. Va. Code §38-2-1 to -39).

Is a preliminary notice required in West Virginia?

Our summary of West Virginia's statute has no general preliminary notice for subcontractors on commercial work. Residential projects and specific project types can differ, so confirm with the statute.

How long is a mechanics lien valid in West Virginia?

Unless you sue to enforce it within 6 months after recording the lien, the lien expires.

What is the maximum retainage in West Virginia?

We haven't reduced West Virginia's retainage rules to one number; they depend on the agency, contract size or contract date. Verify with W. Va. Code §5-22 (public).

How fast must a general contractor pay subcontractors in West Virginia?

We don't have one prompt payment number on file for West Virginia; timing depends on the contract and the agency. Verify with W. Va. Code §5-22 (public).

Can I file a lien on a public project in West Virginia?

No. Public property can't be liened, so subs and suppliers claim against the GC's payment bond under West Virginia's public bond law (W. Va. Code §38-2-39). Its deadlines vary by agency, so verify them before the job starts.