Skip to content
Profound Estimates
Pricing and markup For GCs and subs

Change Order Pricing Calculator

Price extra work from labor, material, equipment and subcontract costs, apply overhead, profit, sub markup and bond the way most contracts allow, and download a change order request with full backup.

  • Free, no sign-up to calculate
  • Download as PDF
  • Reviewed September 27, 2026

Change

Labor

Use burdened rates. The labor burden calculator gives you one.

$10,080.00
  • $
  • $
  • $

Material

$4,409.20
  • $
  • $
  • $

Equipment

$420.00
  • $

Subcontracts

$3,850.00
  • $

Markups

Use the percentages your contract allows.

%

On self-performed cost

%

On cost plus overhead

%
%
%
days
Change order amount
$22,680.65
18.9% over raw cost
Schedule impact
3 days
176 labor hours

How the price builds up

Labor
Material and tax
Equipment
Overhead and profit
Subs and markup
Bond
Total
CostAddedTotal

Summary

Amount
Labor$10,080.00
Material$4,409.20
Sales tax (7.00%)$308.64
Equipment$420.00
Overhead (10.0%)$1,521.78
Profit (10.0%)$1,673.96
Subcontracts$3,850.00
Sub markup (5.0%)$192.50
Bond (1.00%)$224.56
Total$22,680.65

Download your results

A change order request with full cost backup and signature lines.

Your inputs stay in your browser. Results are estimates for planning, not professional, tax or legal advice.

Why change orders get rejected or underpaid

Extra work is where contractors should earn a fair margin, yet change orders are often priced in a hurry on the back of a field ticket. The common problems are predictable: a labor rate without burden, material without tax, a markup the contract doesn’t allow, no request for time, or a lump sum with no backup that the owner’s reviewer sends back for detail.

A change order request that shows its math is approved faster and is much harder to cut.

How the calculator works

  1. Labor. Hours × burdened rate for each classification or crew. The total hours are shown so the reviewer can check productivity.
  2. Material. Quantity × unit cost, then sales tax on the material subtotal.
  3. Equipment. Quantity × unit cost, for rentals or company-owned equipment at an internal rate.
  4. Overhead is applied to self-performed cost (labor + material with tax + equipment).
  5. Profit is applied to self-performed cost plus overhead.
  6. Subcontracts are added at cost, and your sub markup is applied to them separately.
  7. Bond is applied to everything above.

The request also shows the effective markup: how much the total is over raw cost. It’s a quick check against what the contract allows in total.

A worked example

An owner asks the GC to add two exam rooms in the east wing after framing inspection (RFI 014 / ASI 3). The drywall contractor prices it:

Item Amount
Labor: 176 hours (framing, hang and finish, foreman) $10,080.00
Material: studs and track, 88 sheets Type X, finishing supplies $4,409.20
Sales tax on material (7%) $308.64
Equipment: scissor lift, 1 week $420.00
Overhead (10% of self-performed cost) $1,521.78
Profit (10% of cost plus overhead) $1,673.96
Subcontract: electrical, 6 devices and 4 fixtures $3,850.00
Markup on subcontract (5%) $192.50
Bond (1%) $224.56
Total change order amount $22,680.65

Self-performed cost is $15,217.84. Overhead brings it to $16,739.62 and profit to $18,413.58. Add the electrical sub with its 5% markup and the 1% bond, and the request totals $22,680.65, an effective markup of 18.95% over raw cost. The contractor also asks for 3 calendar days.

The labor line is the one reviewers question most. Show hours by crew, not just a dollar amount, and use a rate you can back up with payroll records.

Tips for getting change orders approved

  • Price it before you build it. Most contracts require written authorization before extra work starts. If the work must proceed immediately, get a signed field directive and track time and material daily.
  • Reference the source. Cite the RFI, ASI, bulletin, or directive number and date. It ties the cost to a documented change in scope.
  • Include every cost. Supervision, cleanup, protection of finished work, extra mobilizations and small tools are real costs of extra work.
  • Separate markups the way the contract does. If the contract allows different rates for self-performed and subcontracted work, keep them separate, as this calculator does.
  • Track unsigned requests. Keep a log of pending change orders and follow up weekly. Unapproved work is unbilled work.

Get the labor rate right with the labor burden calculator, and check that your markups cover company overhead with the overhead and markup planner. Many change orders come from work that was excluded in the original bid, which is why clear lines from the inclusions and exclusions library pay off later.

Frequently asked questions

What markup is allowed on a change order?

Your contract decides. Many AIA-based and public contracts allow 10% to 15% for overhead and profit on self-performed work and 5% to 10% on subcontracted work, sometimes with overhead and profit stated separately. Read the changes clause before you price, because a markup above the allowed rate is the fastest way to get a change order rejected.

Why is profit calculated on cost plus overhead?

That's how most contracts and industry forms stack the markups: overhead is added to cost, and profit is added to the resulting subtotal. It gives a slightly higher number than adding both to raw cost. If your contract says both apply to cost only, add them together in the overhead field and set profit to zero.

Should I include time in a change order?

Yes, whenever the change affects the critical path. Ask for calendar days in the same request. Many contracts treat a signed change order without a time extension as agreement that the schedule isn't affected, which can waive a later delay claim.

What labor rate should I use?

Use your burdened cost per hour: wages plus payroll taxes, insurance and benefits. Most contracts let you recover that cost and then add the allowed markup. The labor burden calculator on this site gives you the rate.

What backup should go with a change order request?

The request itself, the reason and reference (RFI, ASI, field directive or owner request), a cost breakdown by labor, material, equipment and subcontracts, supplier and sub quotes, and any photos or marked-up drawings. The PDF from this tool covers the first three.

Need the whole estimate?

Our estimators price complete projects and single trades from your plans, with labor, material and equipment broken out by CSI division.

Learn about the service