General Conditions Estimator

Estimate jobsite overhead across the schedule: project staff, temporary facilities and utilities, cleanup, equipment and insurance, with totals by category and the cost of every month of delay.

  • Free, no sign-up to calculate
  • Download as PDF or Excel
  • Reviewed September 27, 2026

Project

months
$

Excluding general conditions, fee and bond

General conditions
$368,700
6.58% of construction
Per month
$36,870
Over 10 months
Cost of one month's delay
$24,545
Time-based lines only
Line items
15
6 categories

By category

Project staff: $256,500 (69.6%)Temporary facilities: $22,700 (6.2%)Temporary utilities: $14,500 (3.9%)Safety and cleanup: $38,000 (10.3%)Equipment: $23,000 (6.2%)Permits, insurance and bonds: $14,000 (3.8%)
Total
$368,700
  • Project staff$256,50069.6%
  • Temporary facilities$22,7006.2%
  • Temporary utilities$14,5003.9%
  • Safety and cleanup$38,00010.3%
  • Equipment$23,0006.2%
  • Permits, insurance and bonds$14,0003.8%

Largest line items

  • Superintendent
    $130,000
  • Project manager (50%)
    $72,500
  • Assistant superintendent
    $54,000
  • Telehandler
    $23,000
  • Dumpster pulls (30 yd)
    $21,850
  • Builder's risk insurance
    $14,000

Project staff

$256,500
ItemQtyUnitRateDurationTotal
$
$72,500
$
$130,000
$
$54,000

Temporary facilities

$22,700
ItemQtyUnitRateDurationTotal
$
$8,500
$
-$3,200
$
$11,000

Temporary utilities

$14,500
ItemQtyUnitRateDurationTotal
$
$9,000
$
$2,500
$
$3,000

Safety and cleanup

$38,000
ItemQtyUnitRateDurationTotal
$
$4,950
$
-$21,850
$
-$7,200
$
$4,000

Equipment

$23,000
ItemQtyUnitRateDurationTotal
$
$23,000

Permits, insurance and bonds

$14,000
ItemQtyUnitRateDurationTotal
$
-$14,000

Other

$0

Schedule risk

Monthly and weekly costs add up to $24,545 for every month the job runs long. Leave a duration blank to use the full 10-month schedule.

Download your results

A category-by-category estimate, or an Excel sheet with live formulas.

Your inputs stay in your browser. Results are estimates for planning, not professional, tax or legal advice.

What belongs in general conditions

General conditions are the cost of running this jobsite. A useful test: if the project didn’t exist, would you still pay this cost? If not, and it isn’t part of a trade’s scope, it’s a general condition. Typical categories:

  • Project staff: project manager (often a share of their time), superintendent, assistant superintendent, project engineer, with burden.
  • Temporary facilities: office trailer and its setup, storage containers, fencing, signage, barricades.
  • Temporary utilities: power, water, internet and phones, temporary heat or cooling.
  • Safety and cleanup: toilets, dumpsters, daily and final cleaning, safety supplies and signage.
  • Equipment: forklifts, telehandlers, hoists and small equipment used by the GC rather than a trade.
  • Permits, insurance and bonds: builder’s risk, job-specific permits, and bond premiums when carried here.

How the estimator works

Each line has a quantity, a unit and a rate.

  • Per month and per week lines run for the project duration unless you enter a shorter duration for that line (in months or weeks). An assistant superintendent who’s on site for six months of a ten-month job gets a duration of 6.
  • Each lines are quantity × rate, for items like dumpster pulls.
  • Lump sum lines are fixed, for items like trailer delivery and removal or a final clean.

The estimator totals each category, shows general conditions as a percentage of construction cost, and divides the total by the duration to get an average cost per month.

Cost of delay adds up only the time-based lines at their monthly rate. It’s what each extra month would cost if the schedule slipped.

A worked example

A GC is estimating a two-story, 24,000 sq ft medical office building with $5.6 million of construction cost and a 10-month schedule.

Category Total Share
Project staff $256,500 69.6%
Safety and cleanup $38,000 10.3%
Equipment $23,000 6.2%
Temporary facilities $22,700 6.2%
Temporary utilities $14,500 3.9%
Permits, insurance and bonds $14,000 3.8%
Total $368,700 100%

The project staff line includes half of a project manager’s time at $14,500 a month, a full-time superintendent at $13,000, and an assistant superintendent at $9,000 for six months. Safety and cleanup includes 38 dumpster pulls at $575 each and a $7,200 final clean.

General conditions come to 6.58% of construction cost, an average of $36,870 a month. The monthly and weekly lines add up to $24,545 for every month the job runs over. A two-month delay would add about $49,000 before any claim for extended overhead.

Supervision is almost always the largest line. If your general conditions look light, check that every person is on for the full time they’ll really be needed, including closeout and punch list.

Common misses

  • Closeout time. Supervision and the trailer rarely leave the day of substantial completion. Add a month for punch list and closeout on most jobs.
  • Mobilization and demobilization. Trailer delivery, setup, utility hookups and removal are often forgotten because they aren’t monthly.
  • Winter and weather. Temporary heat, enclosures and snow removal can be significant on a winter schedule.
  • Owner requirements. Check Division 01 for field offices for the owner’s representative, progress photography, as-built documentation and special cleaning requirements.

General conditions sit inside your estimate. Company-wide costs belong in your markup, which you can find with the overhead and markup planner. To compare the trade bids that make up the rest of the estimate, use the bid leveling matrix, and to see how the job’s billing and retainage affect your cash, try the cash flow forecaster.

Frequently asked questions

What are general conditions in construction?

General conditions are the costs of running a specific jobsite that aren't part of any one trade's work: project management and supervision, site trailers, temporary utilities, fencing, toilets, dumpsters, cleanup, safety, hoisting and job-specific insurance. They belong in the estimate for that job, unlike company overhead.

What percentage of construction cost are general conditions?

Commonly 5% to 15% of construction cost. Short, simple projects with a high cost per square foot sit at the low end. Long schedules, occupied buildings, tight urban sites and projects with heavy supervision requirements sit at the high end. The percentage is a sanity check, not a way to price them.

Are general conditions the same as general requirements?

They overlap. General requirements is CSI Division 01, which describes the administrative and temporary requirements in the specifications. General conditions usually means the cost of meeting them, although some contracts use general conditions for the legal terms of the contract and general requirements for the costs.

Why does the calculator show a cost of delay?

Most general conditions are time-based. If the job runs a month longer, you keep paying for the superintendent, the trailer, the fencing and the utilities. Knowing that monthly cost helps you price schedule risk and support a claim for extended general conditions when a delay isn't your fault.

Should the superintendent be in general conditions or overhead?

If the superintendent is assigned to this job, put their cost in general conditions for the months they're on site, including burden. Only people who support all jobs, such as an operations manager, belong in company overhead.