Skip to content
Profound Estimates
Getting paid For GCs and subs

Schedule of Values & Pay Application Builder

Build a schedule of values once, then bill each period by percent complete or dollar amount, with stored materials, retainage and previous billings carried forward. Download a pay application PDF with a continuation sheet, or an Excel workbook with live formulas.

  • Free, no sign-up to calculate
  • Download as PDF or Excel
  • Reviewed September 28, 2026

Application

%
%
$

Line 6 of your last approved application

Enter progress as
Current payment due
$158,859
Application 4
Complete and stored
71.0%
$383,480 of $539,800
Retainage held
$38,348
$4,950 on stored materials
Balance to finish
$194,668
Including retainage

Continuation sheet

Enter each line's percent complete to date; this period's billing is worked out for you. Stored materials are billed separately.

ItemDescriptionScheduled valuePrevious% to dateStoredTo date%BalanceRetainageCO
$
$
%
$3,800 this period
$
$26,60070%$11,400$2,660
$
$
%
$650 this period
$
$3,90060%$2,600$390
$
$
%
$1,420 this period
$
$12,78090%$1,420$1,278
$
$
%
$0 this period
$
$42,000100%$0$4,200
$
$
%
$38,400 this period
$
$85,70089%$10,300$8,570
$
$
%
$17,600 this period
$
$79,20090%$8,800$7,920
$
$
%
$33,600 this period
$
$58,80070%$25,200$5,880
$
$
%
$7,200 this period
$
$38,20053%$33,800$3,820
$
$
%
$11,550 this period
$
$19,25050%$19,250$1,925
$
$
%
$6,390 this period
$
$10,65050%$10,650$1,065
$
$
%
$0 this period
$
$00%$26,500$0
$
$
%
$6,400 this period
$
$6,40050%$6,400$640
Totals$539,800$206,970$127,010$49,500$383,48071%$156,320$38,348

Starting the next application moves this period into Previous, carries line 6 into Previous certificates and keeps stored materials until you bill them as installed.

Application summary

LineAmount
1Original contract sum$527,000.00
2Net change by change orders$12,800.00
3Contract sum to date$539,800.00
4Total completed and stored to date$383,480.00
5Retainage (10.0% work, 10.0% stored)$38,348.00
6Total earned less retainage$345,132.00
7Less previous certificates$186,273.00
8Current payment due$158,859.00
9Balance to finish, including retainage$194,668.00

Where the contract stands

Billed before: $206,970 (38.3%)This period: $127,010 (23.5%)Stored materials: $49,500 (9.2%)Balance to finish: $156,320 (29.0%)
Contract
$539,800
  • Billed before$206,97038.3%
  • This period$127,01023.5%
  • Stored materials$49,5009.2%
  • Balance to finish$156,32029.0%

Percent complete by line

Work and stored materials to date against each scheduled value.

  • 1. General conditions and mobilization
    70%
  • 2. Submittals and closeout documents
    60%
  • 3. Temporary power and lighting
    90%
  • 4. Underground conduit and site feeders
    100%
  • 5. Service and distribution gear
    89%
  • 6. Branch rough-in, level 1
    90%
  • 7. Branch rough-in, level 2
    70%
  • 8. Lighting fixtures and controls
    53%
  • 9. Fire alarm system
    50%
  • 10. Low-voltage pathways
    50%
  • 11. Devices, trim and testing
    0%
  • CO-1. Added EV charger circuits (change order 1)
    50%

Download your results

A pay application with the summary, certification and continuation sheet, or an Excel workbook with live formulas.

Your inputs stay in your browser. Results are estimates for planning, not professional, tax or legal advice.

Why the pay application is the most important document you send

Every dollar a contractor earns on a job comes in through a pay application. A clean one gets approved and paid on the first pass. A messy one, with lines over 100%, math that doesn’t foot or a previous-payments figure that doesn’t match the last approval, gets sent back, and the payment clock starts over.

The industry’s standard layout has two parts: a one-page application summary that says how much is due, and a continuation sheet that shows the progress on each line of the schedule of values. This builder produces both from one table, carries the numbers from one period to the next, and does the arithmetic that most often goes wrong.

How the builder works

  1. Set up the schedule of values. Each line has an item number, a description and a scheduled value. Approved change orders are separate lines marked CO; they add up to line 2 of the summary.
  2. Enter progress for the period. Choose % complete to type each line’s percent complete to date (the builder works out the dollars billed this period), or $ this period to type the amount directly. Materials stored on site and not yet installed go in the stored column.
  3. Set retainage. One rate for completed work and one for stored materials, as your contract allows.
  4. Enter previous certificates. That’s line 6 from your last approved application.
  5. Check and send. Lines billed past their scheduled value are flagged, and so is an application that works out to a credit.

When the period is approved, Start the next application moves this period’s billing into Previous, carries line 6 into Previous certificates, bumps the application number and leaves stored materials in place until you bill them as installed.

The totals follow the standard continuation-sheet math:

  • Total completed and stored = previous + this period + stored materials
  • Percent complete = total completed and stored ÷ scheduled value
  • Balance to finish = scheduled value − total completed and stored
  • Retainage = (previous + this period) × retainage on work + stored × retainage on stored materials

A worked example

Brightline Electric is billing application 4 on the Riverside Medical Office Building to the GC, Summit Builders, for the period ending September 30, 2026. The schedule of values has 11 base-contract lines and one approved change order for EV charger circuits. Retainage is 10% on work and on stored materials.

This period, the service and distribution gear line goes from 30% to 70% complete ($38,400 of work) and the switchboard sections sitting in the electrical room, $18,500, are billed as stored materials. Lighting fixtures are 10% installed with $31,000 of fixtures stored on site.

Line Application summary Amount
1 Original contract sum $527,000.00
2 Net change by change orders $12,800.00
3 Contract sum to date $539,800.00
4 Total completed and stored to date $383,480.00
5 Retainage ($33,398 on work + $4,950 on stored) $38,348.00
6 Total earned less retainage $345,132.00
7 Less previous certificates for payment $186,273.00
8 Current payment due $158,859.00
9 Balance to finish, including retainage $194,668.00

The job is 71% complete and stored. Stored materials account for $49,500 of the total, so billing them brings in $44,550 this month (after 10% retainage) that would otherwise wait until the gear and fixtures are installed.

Line 9 includes retainage. Of the $194,668 left to collect, $38,348 is money already earned and held back.

Tips for pay applications that get paid

  • Build the schedule of values to match how you’ll measure progress. Separate rough-in and trim, and floors or areas, so percent complete is easy to defend.
  • Keep general conditions and mobilization reasonable. Front-loading helps cash flow, but an unbalanced schedule of values is the first thing a reviewer questions.
  • Bill stored materials with backup. Delivery tickets, photos and an invoice make approval routine.
  • Match line 7 to the last approved application, not your last request. If the GC reduced it, carry their number.
  • Watch lines approaching 100%. Billing past a scheduled value needs a change order, not a bigger percentage.
  • Send it on the day your contract says. Many contracts have a cut-off date; a day late can mean a month late.

The Excel workbook

The Excel download has two sheets. The continuation sheet keeps live formulas for total to date, percent complete, balance and retainage, and the summary sheet pulls its totals from it, with the retainage rates in their own cells. Change a rate or a line and the whole application recalculates.

Retainage and payment timing decide your cash position; see the whole picture with the cash flow and retainage forecaster. Check your state’s retainage cap and prompt pay deadlines with the retainage and prompt payment rules, and price the extra work you’ll add as change order lines with the change order pricing calculator.

Rules by state

Retainage caps, prompt payment deadlines and lien rules differ by state. See how your state treats them before you bill.

Compare all states in one table →

Frequently asked questions

What is a schedule of values?

A schedule of values breaks the contract sum into line items, usually by area, system or phase, that add up to the contract total. Each pay application bills progress against those lines, so the owner or GC can check what's been done. A good schedule of values has enough lines to measure progress fairly without turning every billing into an audit.

What's the difference between the application summary and the continuation sheet?

The continuation sheet is the line-by-line detail: scheduled value, work from previous applications, work this period, materials stored, total to date, percent complete, balance to finish and retainage. The summary rolls those totals into the numbers that matter for payment: contract sum to date, total earned, retainage, previous certificates and the current payment due.

Can I bill for materials stored on site?

Often, if your contract allows it. Materials delivered but not yet installed are billed in the stored materials column, usually with proof of delivery, insurance and sometimes a bill of sale. When they're installed, they move into work completed and come out of stored materials. Retainage can apply to stored materials at its own rate.

What goes on line 7, previous certificates for payment?

The total of what was certified for payment on all earlier applications, which is line 6 (total earned less retainage) of your last approved application. Use the approved number, not what you billed, if the owner or GC cut the last application.

How should change orders appear on a pay application?

Add each approved change order as its own line on the continuation sheet with its own scheduled value, and bill progress on it like any other line. The summary shows the original contract sum and the net change by change orders separately. Don't bill pending changes until they're approved in writing.

Need the whole estimate?

Our estimators price complete projects and single trades from your plans, with labor, material and equipment broken out by CSI division.

Learn about the service