North Dakota mechanics lien and payment rules

As a subcontractor in North Dakota, you have 90 days after your last day furnishing labor or materials to record a mechanics lien. Here are North Dakota's notice, lien, bond claim, retainage and prompt payment rules in plain language, with the statutes and a worked example.

  • Reviewed
  • 3 statutes cited
  • Not legal advice

North Dakota at a glance

Private commercial work, sub hired by the GC, unless noted
Preliminary notice (subs)
No general preliminary notice
Record the lien (subs)
90 days after your last day furnishing labor or materials Verify
Sue to enforce
36 months after your last day furnishing labor or materials Verify
Public retainage cap
Verify with state statute
Private retainage cap
Verify with state statute
GC pays subs within
Verify with state statute

Turn these rules into dates for your job, free in your browser.

Preliminary notices in North Dakota

North Dakota is one of the states with no general preliminary notice for subcontractors on commercial work in our summary. That doesn't mean you can skip paperwork: the lien itself still has a hard deadline, and the other notices below still apply.

Before recording, GCs, subcontractors and suppliers send a notice of intent to lien at least 15 days before the last day to record the lien. Because it counts back from the deadline, waiting until the last week can leave you too late to record at all.

Lien filing deadline in North Dakota

If the GC hired you, you have 90 days after your last day furnishing labor or materials to record a mechanics lien in North Dakota, about the same as the national median of 90 days (counted from last furnishing on a sample job). 23 of the 51 jurisdictions we track use this same lien deadline, which makes it the most common rule.

A lien can be recorded later (up to 3 years) but loses priority against buyers and lenders. Verify this with the statute before relying on it.

The clock starts on your last day furnishing labor or materials under your contract. In many states, warranty visits and punch list work done mainly to extend the deadline don't restart it, so use your last day of real contract work.

Deadline to sue on the lien

To keep the lien alive you must sue to enforce it within 36 months after your last day furnishing labor or materials. That comes to about 1096 days after your last day on the job, about 731 days longer than the national median of 365 days. 45 of the 48 jurisdictions we track have a shorter overall time to sue and 2 have a longer one.

North Dakota counts the suit deadline from last furnishing, not from recording, so recording late eats into the time left to sue.

Or 30 days after an owner's written demand to sue.

How North Dakota compares

Days are counted on a sample job with the lien recorded on its last allowed day, so states that count from recording or from completion can be compared with those that count from your last day on site. The median is across the jurisdictions with a dated rule on file.

North Dakota deadlines vs the national median
Record the lien (from last day)
North Dakota: 90 days
National median: 90 days
Sue to enforce (from last day)
North Dakota: 1,096 days
National median: 365 days

Public and federal projects

Public property can't be liened, so subcontractors and suppliers on state and local public jobs in North Dakota claim against the GC's payment bond instead. We haven't reduced North Dakota's bond claim deadlines to one set of numbers, because they vary by agency and project. The governing law is N.D. Cent. Code §48-01.2-10. Verify the notice and suit deadlines with the statute and the bond itself before the job starts.

Federal jobs in North Dakota follow the Miller Act instead of state law: those hired by a sub or supplier give the prime contractor notice within 90 days of their last furnishing, and suit is due within 1 year, in federal court. Prime contractors on federal work have no lien or bond claim.

Retainage and prompt payment in North Dakota

We haven't reduced North Dakota's retainage and prompt payment rules to single numbers yet: they depend on the agency, the contract size or the contract date. Rather than guess, the table shows "Verify" and the statutes to read are N.D. Cent. Code §48-01.2-13 (public). Your contract's payment terms still matter, and the federal rules below apply on federal work.

Retainage and prompt payment in North Dakota
Public workPrivate workFederal work
Retainage capVerifyVerify10%
ReleaseVerify with state statuteVerify with state statuteReleased with final payment, or earlier once progress is satisfactory.
GC pays subs withinVerifyVerify7 days
Late-payment interestVerifyVerifyTreasury prompt payment rate (reset every January and July)

Not legal advice. Retainage and prompt payment rules differ by agency, contract size and contract date, and change often. Confirm the rules with the current statute, your contract and a construction attorney before relying on them.

Worked example: an electrical sub in North Dakota

An electrical subcontractor hired by the GC on a private apartment building in North Dakota starts work on March 2, 2026 and last furnishes on July 17, 2026. The project is completed on August 28, 2026. Run through North Dakota's rules, those dates give:

Deadlines for the worked example in North Dakota
DeadlineDateCounted from
Notice of intent to lien (15 days before recording) September 30, 2026 The lien deadline
Record the lien October 15, 2026 Verify Last furnishing
Sue to enforce the lien July 17, 2029 Verify Last furnishing

The first deadline on the calendar is “Notice of intent to lien (15 days before recording)” on September 30, 2026.

Rows marked "Verify" depend on facts or readings we can't settle for you. Check them against N.D. Cent. Code §35-27-01 to -28.

Open the lien deadline calculator for North Dakota and enter your own dates to get this table for your job, with countdowns and a PDF deadline calendar.

Check your own dates with the free tools

Statutes cited

  • N.D. Cent. Code §35-27-01 to -28
  • N.D. Cent. Code §48-01.2-10 (public bonds)
  • N.D. Cent. Code §48-01.2-13 (public)
  • Federal work in North Dakota: 40 U.S.C. §3131 to §3134 (Miller Act)

Not legal advice. Lien and bond claim rules change and have exceptions for project type, contract terms and how notices are served. Confirm every deadline with the current statute or a construction attorney in the project's state before relying on it. Rules shown as "Verify with state statute" have exceptions or variations we could not reduce to one number.

North Dakota lien and payment FAQs

How long do I have to file a mechanics lien in North Dakota?

If you're a subcontractor or supplier hired by the GC, you have 90 days after your last day furnishing labor or materials. A lien can be recorded later (up to 3 years) but loses priority against buyers and lenders. Check the exact date for your job with the free lien deadline calculator, and confirm it with the statute (N.D. Cent. Code §35-27-01 to -28).

Is a preliminary notice required in North Dakota?

Our summary of North Dakota's statute has no general preliminary notice for subcontractors on commercial work, but other notices apply before or after recording the lien. Residential projects and specific project types can differ, so confirm with the statute.

How long is a mechanics lien valid in North Dakota?

Unless you sue to enforce it within 36 months after your last day furnishing labor or materials, the lien expires. Or 30 days after an owner's written demand to sue.

What is the maximum retainage in North Dakota?

We haven't reduced North Dakota's retainage rules to one number; they depend on the agency, contract size or contract date. Verify with N.D. Cent. Code §48-01.2-13 (public).

How fast must a general contractor pay subcontractors in North Dakota?

We don't have one prompt payment number on file for North Dakota; timing depends on the contract and the agency. Verify with N.D. Cent. Code §48-01.2-13 (public).

Can I file a lien on a public project in North Dakota?

No. Public property can't be liened, so subs and suppliers claim against the GC's payment bond under North Dakota's public bond law (N.D. Cent. Code §48-01.2-10). Its deadlines vary by agency, so verify them before the job starts.

Neighboring states

Working across the state line? Rules change at the border, even on the same kind of job.

Same lien deadline (90 days): Connecticut , Delaware , Florida , Georgia .