Skip to content
Profound Estimates

State guide

Colorado mechanics lien and payment rules

As a subcontractor in Colorado, you have 4 months after your last day furnishing labor or materials to record a mechanics lien. Here are Colorado's notice, lien, bond claim, retainage and prompt payment rules in plain language, with the statutes and a worked example.

  • Reviewed
  • 4 statutes cited
  • Not legal advice

Colorado at a glance

Private commercial work, sub hired by the GC, unless noted
Preliminary notice (subs)
No general preliminary notice
Record the lien (subs)
4 months after your last day furnishing labor or materials
Sue to enforce
6 months after your last day furnishing labor or materials
Public retainage cap
Up to 5%
Private retainage cap
Verify with state statute
GC pays subs within
7 days of receiving payment From the public work rules.

Turn these rules into dates for your job, free in your browser.

Preliminary notices in Colorado

Colorado is one of the states with no general preliminary notice for subcontractors on commercial work in our summary. That doesn't mean you can skip paperwork: the lien itself still has a hard deadline, and the other notices below still apply.

Before recording, GCs, subcontractors and suppliers send a notice of intent to lien at least 10 days before the last day to record the lien. Because it counts back from the deadline, waiting until the last week can leave you too late to record at all.

Lien filing deadline in Colorado

If the GC hired you, you have 4 months after your last day furnishing labor or materials to record a mechanics lien in Colorado, about 32 days longer than the national median of 90 days (counted from last furnishing on a sample job). 40 of the 51 jurisdictions we track have a shorter lien deadline and 7 have a longer one.

Laborers paid by the day: 2 months.

The clock starts on your last day furnishing labor or materials under your contract. In many states, warranty visits and punch list work done mainly to extend the deadline don't restart it, so use your last day of real contract work.

Deadline to sue on the lien

To keep the lien alive you must sue to enforce it within 6 months after your last day furnishing labor or materials. That comes to about 183 days after your last day on the job, about 182 days shorter than the national median of 365 days. 6 of the 48 jurisdictions we track have a shorter overall time to sue and 39 have a longer one.

Colorado counts the suit deadline from last furnishing, not from recording, so recording late eats into the time left to sue.

Counted from completion of the work or your last furnishing.

How Colorado compares

Days are counted on a sample job with the lien recorded on its last allowed day, so states that count from recording or from completion can be compared with those that count from your last day on site. The median is across the jurisdictions with a dated rule on file.

Colorado deadlines vs the national median
Record the lien (from last day)
Colorado: 122 days
National median: 90 days
Sue to enforce (from last day)
Colorado: 183 days
National median: 365 days

Public and federal projects

Public property can't be liened, so subcontractors and suppliers on state and local public jobs in Colorado claim against the GC's payment bond instead. We haven't reduced Colorado's bond claim deadlines to one set of numbers, because they vary by agency and project. The governing law is Colo. Rev. Stat. §38-26-107. Verify the notice and suit deadlines with the statute and the bond itself before the job starts.

Federal jobs in Colorado follow the Miller Act instead of state law: those hired by a sub or supplier give the prime contractor notice within 90 days of their last furnishing, and suit is due within 1 year, in federal court. Prime contractors on federal work have no lien or bond claim.

Retainage and prompt payment in Colorado

On public work the cap is 5%, the most common cap among states that set one. Up to 5% of the total contract price.

On private work we have no statutory cap on file, so retainage is usually whatever the contract says. Read the retainage and release clauses before you sign.

Once the GC is paid, it has 7 days on public work to pay its subs. GC pays subs within 7 days of receiving payment.

Retainage and prompt payment in Colorado
Public workPrivate workFederal work
Retainage cap5%Verify10%
ReleaseWith final settlement after the published notice of final settlement.Verify with state statuteReleased with final payment, or earlier once progress is satisfactory.
GC pays subs within7 daysVerify7 days
Late-payment interestVerifyVerifyTreasury prompt payment rate (reset every January and July)

Not legal advice. Retainage and prompt payment rules differ by agency, contract size and contract date, and change often. Confirm the rules with the current statute, your contract and a construction attorney before relying on them.

Worked example: a plumbing sub in Colorado

A plumbing subcontractor hired by the GC on a private elementary school addition in Colorado starts work on March 2, 2026 and last furnishes on July 17, 2026. The project is completed on August 28, 2026. Run through Colorado's rules, those dates give:

Deadlines for the worked example in Colorado
DeadlineDateCounted from
Notice of intent to lien (10 days before recording) November 7, 2026 Weekend The lien deadline
Record the lien November 17, 2026 Last furnishing
Sue to enforce the lien January 17, 2027 Weekend Last furnishing

The first deadline on the calendar is “Notice of intent to lien (10 days before recording)” on November 7, 2026.

2 dates land on a weekend (November 7, 2026, January 17, 2027). Not every state rolls a deadline to Monday, so the safe move is to record or serve by the Friday before.

Open the lien deadline calculator for Colorado and enter your own dates to get this table for your job, with countdowns and a PDF deadline calendar.

Check your own dates with the free tools

Statutes cited

  • Colo. Rev. Stat. §38-22-101 to -133
  • Colo. Rev. Stat. §38-26-107 (public)
  • Colo. Rev. Stat. §24-91-103 (public)
  • Colo. Rev. Stat. §38-26-107 (final settlement)
  • Federal work in Colorado: 40 U.S.C. §3131 to §3134 (Miller Act)

Not legal advice. Lien and bond claim rules change and have exceptions for project type, contract terms and how notices are served. Confirm every deadline with the current statute or a construction attorney in the project's state before relying on it. Rules shown as "Verify with state statute" have exceptions or variations we could not reduce to one number.

Colorado lien and payment FAQs

How long do I have to file a mechanics lien in Colorado?

If you're a subcontractor or supplier hired by the GC, you have 4 months after your last day furnishing labor or materials. Laborers paid by the day: 2 months. Check the exact date for your job with the free lien deadline calculator, and confirm it with the statute (Colo. Rev. Stat. §38-22-101 to -133).

Is a preliminary notice required in Colorado?

Our summary of Colorado's statute has no general preliminary notice for subcontractors on commercial work, but other notices apply before or after recording the lien. Residential projects and specific project types can differ, so confirm with the statute.

How long is a mechanics lien valid in Colorado?

Unless you sue to enforce it within 6 months after your last day furnishing labor or materials, the lien expires. Counted from completion of the work or your last furnishing.

What is the maximum retainage in Colorado?

Up to 5% on public work (Up to 5% of the total contract price). We have no private retainage cap on file, so the contract usually governs.

How fast must a general contractor pay subcontractors in Colorado?

GC pays subs within 7 days of receiving payment.

Can I file a lien on a public project in Colorado?

No. Public property can't be liened, so subs and suppliers claim against the GC's payment bond under Colorado's public bond law (Colo. Rev. Stat. §38-26-107). Its deadlines vary by agency, so verify them before the job starts.

Neighboring states

Working across the state line? Rules change at the border, even on the same kind of job.

Same lien deadline (4 months): Alabama , Illinois .