Skip to content
Profound Estimates

State guide

Arizona mechanics lien and payment rules

As a subcontractor in Arizona, you have 120 days after completion of the project to record a mechanics lien, and a preliminary 20-day notice is required. Here are Arizona's notice, lien, bond claim, retainage and prompt payment rules in plain language, with the statutes and a worked example.

  • Reviewed
  • 4 statutes cited
  • Not legal advice

Arizona at a glance

Private commercial work, sub hired by the GC, unless noted
Preliminary notice (subs)
20 days after your first day furnishing labor or materials Required. Preliminary 20-day notice.
Record the lien (subs)
120 days after completion of the project
Sue to enforce
6 months after recording the lien
Public retainage cap
Up to 10%
Private retainage cap
Up to 10%
GC pays subs within
7 days of receiving payment From the private work rules.

Turn these rules into dates for your job, free in your browser.

Preliminary notices in Arizona

Subcontractors and suppliers on a private job in Arizona serve a preliminary 20-day notice within 20 days after your first day furnishing labor or materials. It is required. That is tighter than the 26-day middle of the states that set a fixed window, so it belongs on day one of the job.

A late notice covers only work furnished in the 20 days before it's served.

General contractors have their own step: preliminary 20-day notice within 20 days after your first day furnishing labor or materials, optional but recommended. Arizona's notice statute has been read to reach prime contractors too; many GCs serve one to be safe.

Lien filing deadline in Arizona

If the GC hired you, you have 120 days after completion of the project to record a mechanics lien in Arizona, about 30 days longer than the national median of 90 days (counted from last furnishing on a sample job). 9 of the 51 jurisdictions we track use this same lien deadline.

60 days after a recorded notice of completion, if that is earlier.

Note what the clock counts from: completion of the project, not your own last day. A trade that finishes early may have more time than the number suggests, but the completion date is often unclear. The calculator uses your last furnishing date when you leave completion blank, which gives the earlier, safer date.

Deadline to sue on the lien

To keep the lien alive you must sue to enforce it within 6 months after recording the lien. If you record on the last possible day, that is about 302 days after your last day on the job, about 63 days shorter than the national median of 365 days. 19 of the 48 jurisdictions we track have a shorter overall time to sue and 27 have a longer one.

Because the clock counts from recording, recording early also moves the lawsuit deadline earlier.

How Arizona compares

Days are counted on a sample job with the lien recorded on its last allowed day, so states that count from recording or from completion can be compared with those that count from your last day on site. The median is across the jurisdictions with a dated rule on file.

Arizona deadlines vs the national median
Preliminary notice (from first day)
Arizona: 20 days
National median: 25.5 days
Record the lien (from last day)
Arizona: 120 days
National median: 90 days
Sue to enforce (from last day)
Arizona: 302 days
National median: 365 days

Public and federal projects

Public property can't be liened, so subcontractors and suppliers on state and local public jobs in Arizona claim against the GC's payment bond instead. We haven't reduced Arizona's bond claim deadlines to one set of numbers, because they vary by agency and project. The governing law is Ariz. Rev. Stat. §34-223. Verify the notice and suit deadlines with the statute and the bond itself before the job starts.

Federal jobs in Arizona follow the Miller Act instead of state law: those hired by a sub or supplier give the prime contractor notice within 90 days of their last furnishing, and suit is due within 1 year, in federal court. Prime contractors on federal work have no lien or bond claim.

Retainage and prompt payment in Arizona

On public work the cap is 10%, above the 5% median of states that set one. Up to 10%, dropping to 5% once the work is 50% complete if progress is satisfactory. It also steps down partway through the job, so check that your pay applications reduce retainage when the project reaches the threshold.

Private work has a cap too: 10%. Up to 10%, dropping to 5% at 50% complete.

Once the GC is paid, it has 7 days on private work to pay its subs. Owner pays within 7 days of approving a pay request (approval within 14 days); GC pays subs within 7 days of receipt.

Late payments carry interest of 1.5% per month. That turns a slow payment into a number you can put in a demand letter.

Retainage and prompt payment in Arizona
Public workPrivate workFederal work
Retainage cap10%10%10%
ReleaseWith final payment after completion.Released with final payment; flows down to subs within 7 days of receipt.Released with final payment, or earlier once progress is satisfactory.
GC pays subs withinVerify7 days7 days
Late-payment interestVerify1.5% per month (18% a year)Treasury prompt payment rate (reset every January and July)

Not legal advice. Retainage and prompt payment rules differ by agency, contract size and contract date, and change often. Confirm the rules with the current statute, your contract and a construction attorney before relying on them.

Worked example: a concrete sub in Arizona

A concrete subcontractor hired by the GC on a private bank branch in Arizona starts work on March 2, 2026 and last furnishes on July 17, 2026. The project is completed on August 28, 2026. Run through Arizona's rules, those dates give:

Deadlines for the worked example in Arizona
DeadlineDateCounted from
Preliminary 20-day notice March 22, 2026 Weekend First furnishing
Record the lien December 26, 2026 Weekend Project completion
Sue to enforce the lien June 26, 2027 Weekend Lien recording

The first deadline on the calendar is “Preliminary 20-day notice” on March 22, 2026, counted from the day the crew started, long before any payment is late.

3 dates land on a weekend (March 22, 2026, December 26, 2026, June 26, 2027). Not every state rolls a deadline to Monday, so the safe move is to record or serve by the Friday before.

Because Arizona counts from project completion (August 28), not the sub's last day (July 17), the lien deadline is later than a last-furnishing state would give.

Open the lien deadline calculator for Arizona and enter your own dates to get this table for your job, with countdowns and a PDF deadline calendar.

Check your own dates with the free tools

Statutes cited

  • Ariz. Rev. Stat. §33-981 to -1008
  • Ariz. Rev. Stat. §34-223 (public bonds)
  • Ariz. Rev. Stat. §34-221 (public)
  • Ariz. Rev. Stat. §32-1129 to -1129.07 (private prompt pay)
  • Federal work in Arizona: 40 U.S.C. §3131 to §3134 (Miller Act)

Not legal advice. Lien and bond claim rules change and have exceptions for project type, contract terms and how notices are served. Confirm every deadline with the current statute or a construction attorney in the project's state before relying on it. Rules shown as "Verify with state statute" have exceptions or variations we could not reduce to one number.

Arizona lien and payment FAQs

How long do I have to file a mechanics lien in Arizona?

If you're a subcontractor or supplier hired by the GC, you have 120 days after completion of the project. 60 days after a recorded notice of completion, if that is earlier. Check the exact date for your job with the free lien deadline calculator, and confirm it with the statute (Ariz. Rev. Stat. §33-981 to -1008).

Is a preliminary notice required in Arizona?

Subcontractors and suppliers give a preliminary 20-day notice within 20 days after your first day furnishing labor or materials. It is required. A late notice covers only work furnished in the 20 days before it's served.

How long is a mechanics lien valid in Arizona?

Unless you sue to enforce it within 6 months after recording the lien, the lien expires.

What is the maximum retainage in Arizona?

Up to 10% on public work (Up to 10%, dropping to 5% once the work is 50% complete if progress is satisfactory). Up to 10% on private work (Up to 10%, dropping to 5% at 50% complete).

How fast must a general contractor pay subcontractors in Arizona?

Owner pays within 7 days of approving a pay request (approval within 14 days); GC pays subs within 7 days of receipt. Late payments carry interest of 1.5% per month.

Can I file a lien on a public project in Arizona?

No. Public property can't be liened, so subs and suppliers claim against the GC's payment bond under Arizona's public bond law (Ariz. Rev. Stat. §34-223). Its deadlines vary by agency, so verify them before the job starts.

Neighboring states

Working across the state line? Rules change at the border, even on the same kind of job.