Skip to content
Profound Estimates

State guide

Nevada mechanics lien and payment rules

As a subcontractor in Nevada, you have 90 days after your last day furnishing labor or materials to record a mechanics lien, and a notice of right to lien is required. Here are Nevada's notice, lien, bond claim, retainage and prompt payment rules in plain language, with the statutes and a worked example.

  • Reviewed
  • 4 statutes cited
  • Not legal advice

Nevada at a glance

Private commercial work, sub hired by the GC, unless noted
Preliminary notice (subs)
31 days after your first day furnishing labor or materials Required. Notice of right to lien.
Record the lien (subs)
90 days after your last day furnishing labor or materials
Sue to enforce
6 months after recording the lien
Public retainage cap
Up to 5%
Private retainage cap
Verify with state statute
GC pays subs within
10 days of receiving payment From the private work rules.

Turn these rules into dates for your job, free in your browser.

Preliminary notices in Nevada

Subcontractors and suppliers on a private job in Nevada serve a notice of right to lien within 31 days after your first day furnishing labor or materials. It is required. That is longer than most states that set a fixed window (the middle is about 26 days), but a late notice can still cost you.

Before recording, subcontractors and suppliers send a notice of intent to lien at least 15 days before the last day to record the lien. Because it counts back from the deadline, waiting until the last week can leave you too late to record at all.

Lien filing deadline in Nevada

If the GC hired you, you have 90 days after your last day furnishing labor or materials to record a mechanics lien in Nevada, about the same as the national median of 90 days (counted from last furnishing on a sample job). 23 of the 51 jurisdictions we track use this same lien deadline, which makes it the most common rule.

Counted from the later of project completion and your last work; 40 days after a recorded notice of completion, if earlier.

The clock starts on your last day furnishing labor or materials under your contract. In many states, warranty visits and punch list work done mainly to extend the deadline don't restart it, so use your last day of real contract work.

Deadline to sue on the lien

To keep the lien alive you must sue to enforce it within 6 months after recording the lien. If you record on the last possible day, that is about 271 days after your last day on the job, about 94 days shorter than the national median of 365 days. 14 of the 48 jurisdictions we track have a shorter overall time to sue and 32 have a longer one.

Because the clock counts from recording, recording early also moves the lawsuit deadline earlier.

How Nevada compares

Days are counted on a sample job with the lien recorded on its last allowed day, so states that count from recording or from completion can be compared with those that count from your last day on site. The median is across the jurisdictions with a dated rule on file.

Nevada deadlines vs the national median
Preliminary notice (from first day)
Nevada: 31 days
National median: 25.5 days
Record the lien (from last day)
Nevada: 90 days
National median: 90 days
Sue to enforce (from last day)
Nevada: 271 days
National median: 365 days

Public and federal projects

Public property can't be liened, so subcontractors and suppliers on state and local public jobs in Nevada claim against the GC's payment bond instead. We haven't reduced Nevada's bond claim deadlines to one set of numbers, because they vary by agency and project. The governing law is Nev. Rev. Stat. §339.015 to .065. Verify the notice and suit deadlines with the statute and the bond itself before the job starts.

Federal jobs in Nevada follow the Miller Act instead of state law: those hired by a sub or supplier give the prime contractor notice within 90 days of their last furnishing, and suit is due within 1 year, in federal court. Prime contractors on federal work have no lien or bond claim.

Retainage and prompt payment in Nevada

On public work the cap is 5%, the most common cap among states that set one. Up to 5% of each progress payment.

On private work we have no statutory cap on file, so retainage is usually whatever the contract says. Read the retainage and release clauses before you sign.

Once the GC is paid, it has 10 days on private work to pay its subs. Owner pays within 21 days of a pay request; GC pays subs within 10 days of receipt.

Late payments carry interest of prime rate plus 2% per year, a floating rate, so the calculator asks you for the current figure. That turns a slow payment into a number you can put in a demand letter.

Retainage and prompt payment in Nevada
Public workPrivate workFederal work
Retainage cap5%Verify10%
ReleaseAfter completion and acceptance.Verify with state statuteReleased with final payment, or earlier once progress is satisfactory.
GC pays subs withinVerify10 days7 days
Late-payment interestVerifyPrime rate plus 2% per yearTreasury prompt payment rate (reset every January and July)

Not legal advice. Retainage and prompt payment rules differ by agency, contract size and contract date, and change often. Confirm the rules with the current statute, your contract and a construction attorney before relying on them.

Worked example: a painting sub in Nevada

A painting subcontractor hired by the GC on a private medical office building in Nevada starts work on March 2, 2026 and last furnishes on July 17, 2026. The project is completed on August 28, 2026. Run through Nevada's rules, those dates give:

Deadlines for the worked example in Nevada
DeadlineDateCounted from
Notice of right to lien April 2, 2026 First furnishing
Residential notice of intent to lien (15 days before recording) September 30, 2026 The lien deadline
Record the lien October 15, 2026 Last furnishing
Sue to enforce the lien April 15, 2027 Lien recording

The first deadline on the calendar is “Notice of right to lien” on April 2, 2026, counted from the day the crew started, long before any payment is late.

Open the lien deadline calculator for Nevada and enter your own dates to get this table for your job, with countdowns and a PDF deadline calendar.

Check your own dates with the free tools

Statutes cited

  • Nev. Rev. Stat. §108.221 to .246
  • Nev. Rev. Stat. §339.015 to .065 (public bonds)
  • Nev. Rev. Stat. §338.515 to .560 (public)
  • Nev. Rev. Stat. §624.606 to .630 (private)
  • Federal work in Nevada: 40 U.S.C. §3131 to §3134 (Miller Act)

Not legal advice. Lien and bond claim rules change and have exceptions for project type, contract terms and how notices are served. Confirm every deadline with the current statute or a construction attorney in the project's state before relying on it. Rules shown as "Verify with state statute" have exceptions or variations we could not reduce to one number.

Nevada lien and payment FAQs

How long do I have to file a mechanics lien in Nevada?

If you're a subcontractor or supplier hired by the GC, you have 90 days after your last day furnishing labor or materials. Counted from the later of project completion and your last work; 40 days after a recorded notice of completion, if earlier. Check the exact date for your job with the free lien deadline calculator, and confirm it with the statute (Nev. Rev. Stat. §108.221 to .246).

Is a preliminary notice required in Nevada?

Subcontractors and suppliers give a notice of right to lien within 31 days after your first day furnishing labor or materials. It is required.

How long is a mechanics lien valid in Nevada?

Unless you sue to enforce it within 6 months after recording the lien, the lien expires.

What is the maximum retainage in Nevada?

Up to 5% on public work (Up to 5% of each progress payment). We have no private retainage cap on file, so the contract usually governs.

How fast must a general contractor pay subcontractors in Nevada?

Owner pays within 21 days of a pay request; GC pays subs within 10 days of receipt. Late payments carry interest of prime rate plus 2% per year.

Can I file a lien on a public project in Nevada?

No. Public property can't be liened, so subs and suppliers claim against the GC's payment bond under Nevada's public bond law (Nev. Rev. Stat. §339.015 to .065). Its deadlines vary by agency, so verify them before the job starts.

Neighboring states

Working across the state line? Rules change at the border, even on the same kind of job.

Same lien deadline (90 days): Connecticut , Delaware , Florida , Georgia .