State guide

Idaho mechanics lien and payment rules

As a subcontractor in Idaho, you have 90 days after your last day furnishing labor or materials to record a mechanics lien. Here are Idaho's notice, lien, bond claim, retainage and prompt payment rules in plain language, with the statutes and a worked example.

  • Reviewed
  • 3 statutes cited
  • Not legal advice

Idaho at a glance

Private commercial work, sub hired by the GC, unless noted
Preliminary notice (subs)
No general preliminary notice
Record the lien (subs)
90 days after your last day furnishing labor or materials
Sue to enforce
6 months after recording the lien
Public retainage cap
Verify with state statute
Private retainage cap
Verify with state statute
GC pays subs within
Verify with state statute

Turn these rules into dates for your job, free in your browser.

Preliminary notices in Idaho

Idaho is one of the states with no general preliminary notice for subcontractors on commercial work in our summary. That doesn't mean you can skip paperwork: the lien itself still has a hard deadline, and the owner often learns about your claim only when the lien is recorded.

General contractors have their own step: residential disclosure to homeowner before you start work, required only in some cases. Residential contracts over $2,000, before the contract is signed.

Lien filing deadline in Idaho

If the GC hired you, you have 90 days after your last day furnishing labor or materials to record a mechanics lien in Idaho, about the same as the national median of 90 days (counted from last furnishing on a sample job). 23 of the 51 jurisdictions we track use this same lien deadline, which makes it the most common rule.

Serve a copy on the owner within 5 business days after recording.

The clock starts on your last day furnishing labor or materials under your contract. In many states, warranty visits and punch list work done mainly to extend the deadline don't restart it, so use your last day of real contract work.

Deadline to sue on the lien

To keep the lien alive you must sue to enforce it within 6 months after recording the lien. If you record on the last possible day, that is about 271 days after your last day on the job, about 94 days shorter than the national median of 365 days. 14 of the 48 jurisdictions we track have a shorter overall time to sue and 32 have a longer one.

Because the clock counts from recording, recording early also moves the lawsuit deadline earlier.

How Idaho compares

Days are counted on a sample job with the lien recorded on its last allowed day, so states that count from recording or from completion can be compared with those that count from your last day on site. The median is across the jurisdictions with a dated rule on file.

Idaho deadlines vs the national median
Record the lien (from last day)
Idaho: 90 days
National median: 90 days
Sue to enforce (from last day)
Idaho: 271 days
National median: 365 days

Public and federal projects

Public property can't be liened, so subcontractors and suppliers on state and local public jobs in Idaho claim against the GC's payment bond instead. We haven't reduced Idaho's bond claim deadlines to one set of numbers, because they vary by agency and project. The governing law is Idaho Code §54-1925 to -1930. Verify the notice and suit deadlines with the statute and the bond itself before the job starts.

Federal jobs in Idaho follow the Miller Act instead of state law: those hired by a sub or supplier give the prime contractor notice within 90 days of their last furnishing, and suit is due within 1 year, in federal court. Prime contractors on federal work have no lien or bond claim.

Retainage and prompt payment in Idaho

We haven't reduced Idaho's retainage and prompt payment rules to single numbers yet: they depend on the agency, the contract size or the contract date. Rather than guess, the table shows "Verify" and the statutes to read are Idaho Code §67-2301 to -2304 (public). Your contract's payment terms still matter, and the federal rules below apply on federal work.

Retainage and prompt payment in Idaho
Public workPrivate workFederal work
Retainage capVerifyVerify10%
ReleaseVerify with state statuteVerify with state statuteReleased with final payment, or earlier once progress is satisfactory.
GC pays subs withinVerifyVerify7 days
Late-payment interestVerifyVerifyTreasury prompt payment rate (reset every January and July)

Not legal advice. Retainage and prompt payment rules differ by agency, contract size and contract date, and change often. Confirm the rules with the current statute, your contract and a construction attorney before relying on them.

Worked example: an electrical sub in Idaho

An electrical subcontractor hired by the GC on a private elementary school addition in Idaho starts work on March 2, 2026 and last furnishes on July 17, 2026. The project is completed on August 28, 2026. Run through Idaho's rules, those dates give:

Deadlines for the worked example in Idaho
DeadlineDateCounted from
Record the lien October 15, 2026 Last furnishing
Sue to enforce the lien April 15, 2027 Lien recording

The first deadline on the calendar is “Record the lien” on October 15, 2026.

Open the lien deadline calculator for Idaho and enter your own dates to get this table for your job, with countdowns and a PDF deadline calendar.

Check your own dates with the free tools

Statutes cited

  • Idaho Code §45-501 to -525
  • Idaho Code §54-1925 to -1930 (public bonds)
  • Idaho Code §67-2301 to -2304 (public)
  • Federal work in Idaho: 40 U.S.C. §3131 to §3134 (Miller Act)

Not legal advice. Lien and bond claim rules change and have exceptions for project type, contract terms and how notices are served. Confirm every deadline with the current statute or a construction attorney in the project's state before relying on it. Rules shown as "Verify with state statute" have exceptions or variations we could not reduce to one number.

Idaho lien and payment FAQs

How long do I have to file a mechanics lien in Idaho?

If you're a subcontractor or supplier hired by the GC, you have 90 days after your last day furnishing labor or materials. Serve a copy on the owner within 5 business days after recording. Check the exact date for your job with the free lien deadline calculator, and confirm it with the statute (Idaho Code §45-501 to -525).

Is a preliminary notice required in Idaho?

Our summary of Idaho's statute has no general preliminary notice for subcontractors on commercial work. Residential projects and specific project types can differ, so confirm with the statute.

How long is a mechanics lien valid in Idaho?

Unless you sue to enforce it within 6 months after recording the lien, the lien expires.

What is the maximum retainage in Idaho?

We haven't reduced Idaho's retainage rules to one number; they depend on the agency, contract size or contract date. Verify with Idaho Code §67-2301 to -2304 (public).

How fast must a general contractor pay subcontractors in Idaho?

We don't have one prompt payment number on file for Idaho; timing depends on the contract and the agency. Verify with Idaho Code §67-2301 to -2304 (public).

Can I file a lien on a public project in Idaho?

No. Public property can't be liened, so subs and suppliers claim against the GC's payment bond under Idaho's public bond law (Idaho Code §54-1925 to -1930). Its deadlines vary by agency, so verify them before the job starts.