Skip to content
Profound Estimates

State guide

Utah mechanics lien and payment rules

As a subcontractor in Utah, you have 90 days after completion of the project to record a mechanics lien, and a preliminary notice (State Construction Registry) is required. Here are Utah's notice, lien, bond claim, retainage and prompt payment rules in plain language, with the statutes and a worked example.

  • Reviewed
  • 3 statutes cited
  • Not legal advice

Utah at a glance

Private commercial work, sub hired by the GC, unless noted
Preliminary notice (subs)
20 days after your first day furnishing labor or materials Verify Required. Preliminary notice (State Construction Registry).
Record the lien (subs)
90 days after completion of the project
Sue to enforce
180 days after recording the lien
Public retainage cap
Up to 5%
Private retainage cap
Up to 5%
GC pays subs within
Verify with state statute

Turn these rules into dates for your job, free in your browser.

Preliminary notices in Utah

GCs, subcontractors and suppliers on a private job in Utah serve a preliminary notice (State Construction Registry) within 20 days after your first day furnishing labor or materials. It is required. That is tighter than the 26-day middle of the states that set a fixed window, so it belongs on day one of the job.

Filed on the state registry.

Lien filing deadline in Utah

If the GC hired you, you have 90 days after completion of the project to record a mechanics lien in Utah, about the same as the national median of 90 days (counted from last furnishing on a sample job). 23 of the 51 jurisdictions we track use this same lien deadline, which makes it the most common rule.

90 days after final completion if a notice of completion is filed; 180 days if not.

Note what the clock counts from: completion of the project, not your own last day. A trade that finishes early may have more time than the number suggests, but the completion date is often unclear. The calculator uses your last furnishing date when you leave completion blank, which gives the earlier, safer date.

Deadline to sue on the lien

To keep the lien alive you must sue to enforce it within 180 days after recording the lien. If you record on the last possible day, that is about 270 days after your last day on the job, about 95 days shorter than the national median of 365 days. 11 of the 48 jurisdictions we track have a shorter overall time to sue and 34 have a longer one.

Because the clock counts from recording, recording early also moves the lawsuit deadline earlier.

How Utah compares

Days are counted on a sample job with the lien recorded on its last allowed day, so states that count from recording or from completion can be compared with those that count from your last day on site. The median is across the jurisdictions with a dated rule on file.

Utah deadlines vs the national median
Preliminary notice (from first day)
Utah: 20 days
National median: 25.5 days
Record the lien (from last day)
Utah: 90 days
National median: 90 days
Sue to enforce (from last day)
Utah: 270 days
National median: 365 days

Public and federal projects

Public property can't be liened, so subcontractors and suppliers on state and local public jobs in Utah claim against the GC's payment bond instead. We haven't reduced Utah's bond claim deadlines to one set of numbers, because they vary by agency and project. The governing law is Utah Code §63G-6a-1103. Verify the notice and suit deadlines with the statute and the bond itself before the job starts.

Federal jobs in Utah follow the Miller Act instead of state law: those hired by a sub or supplier give the prime contractor notice within 90 days of their last furnishing, and suit is due within 1 year, in federal court. Prime contractors on federal work have no lien or bond claim.

Retainage and prompt payment in Utah

On public work the cap is 5%, the most common cap among states that set one. Up to 5% of each payment.

Private work has a cap too: 5%. Up to 5% of each payment.

Retainage and prompt payment in Utah
Public workPrivate workFederal work
Retainage cap5%5%10%
ReleaseWithin 45 days after substantial completion.Within 45 days after substantial completion.Released with final payment, or earlier once progress is satisfactory.
GC pays subs withinVerifyVerify7 days
Late-payment interestVerifyVerifyTreasury prompt payment rate (reset every January and July)

Not legal advice. Retainage and prompt payment rules differ by agency, contract size and contract date, and change often. Confirm the rules with the current statute, your contract and a construction attorney before relying on them.

Worked example: a drywall sub in Utah

A drywall subcontractor hired by the GC on a private bank branch in Utah starts work on March 2, 2026 and last furnishes on July 17, 2026. The project is completed on August 28, 2026. Run through Utah's rules, those dates give:

Deadlines for the worked example in Utah
DeadlineDateCounted from
Preliminary notice (State Construction Registry) March 22, 2026 WeekendVerify First furnishing
Record the lien November 26, 2026 Project completion
Sue to enforce the lien May 25, 2027 Lien recording

The first deadline on the calendar is “Preliminary notice (State Construction Registry)” on March 22, 2026, counted from the day the crew started, long before any payment is late.

One date lands on a weekend (March 22, 2026). Not every state rolls a deadline to Monday, so the safe move is to record or serve by the Friday before.

Rows marked "Verify" depend on facts or readings we can't settle for you. Check them against Utah Code §38-1a-101 to -804.

Because Utah counts from project completion (August 28), not the sub's last day (July 17), the lien deadline is later than a last-furnishing state would give.

Open the lien deadline calculator for Utah and enter your own dates to get this table for your job, with countdowns and a PDF deadline calendar.

Check your own dates with the free tools

Statutes cited

  • Utah Code §38-1a-101 to -804
  • Utah Code §63G-6a-1103 (public bonds)
  • Utah Code §13-8-5 (retainage)
  • Federal work in Utah: 40 U.S.C. §3131 to §3134 (Miller Act)

Not legal advice. Lien and bond claim rules change and have exceptions for project type, contract terms and how notices are served. Confirm every deadline with the current statute or a construction attorney in the project's state before relying on it. Rules shown as "Verify with state statute" have exceptions or variations we could not reduce to one number.

Utah lien and payment FAQs

How long do I have to file a mechanics lien in Utah?

If you're a subcontractor or supplier hired by the GC, you have 90 days after completion of the project. 90 days after final completion if a notice of completion is filed; 180 days if not. Check the exact date for your job with the free lien deadline calculator, and confirm it with the statute (Utah Code §38-1a-101 to -804).

Is a preliminary notice required in Utah?

GCs, subcontractors and suppliers give a preliminary notice (State Construction Registry) within 20 days after your first day furnishing labor or materials. It is required. Filed on the state registry.

How long is a mechanics lien valid in Utah?

Unless you sue to enforce it within 180 days after recording the lien, the lien expires.

What is the maximum retainage in Utah?

Up to 5% on public work (Up to 5% of each payment). Up to 5% on private work (Up to 5% of each payment).

How fast must a general contractor pay subcontractors in Utah?

We don't have one prompt payment number on file for Utah; timing depends on the contract and the agency. Verify with Utah Code §13-8-5 (retainage).

Can I file a lien on a public project in Utah?

No. Public property can't be liened, so subs and suppliers claim against the GC's payment bond under Utah's public bond law (Utah Code §63G-6a-1103). Its deadlines vary by agency, so verify them before the job starts.

Neighboring states

Working across the state line? Rules change at the border, even on the same kind of job.

Same lien deadline (90 days): California , District of Columbia , Tennessee .