Skip to content
Profound Estimates

State guide

Tennessee mechanics lien and payment rules

As a subcontractor in Tennessee, you have 90 days after completion of the project to record a mechanics lien, and a notice of nonpayment is required only in some cases. Here are Tennessee's notice, lien, bond claim, retainage and prompt payment rules in plain language, with the statutes and a worked example.

  • Reviewed
  • 3 statutes cited
  • Not legal advice

Tennessee at a glance

Private commercial work, sub hired by the GC, unless noted
Preliminary notice (subs)
90 days after the last day of each month you furnish Verify Required only in some cases. Notice of nonpayment.
Record the lien (subs)
90 days after completion of the project
Sue to enforce
90 days after recording the lien Verify
Public retainage cap
Up to 5%
Private retainage cap
Up to 5%
GC pays subs within
Verify with state statute

Turn these rules into dates for your job, free in your browser.

Preliminary notices in Tennessee

Tennessee's notice rule runs month by month. Subcontractors and suppliers send a notice of nonpayment 90 days after the last day of each month you furnish, so every month of unpaid work has its own deadline. Remote contractors (no contract with the owner): within 90 days after the last day of each month with unpaid work.

This is the rule that catches people out: by the time a second invoice goes unpaid, the notice for the first month may already be due. Put the dates in your calendar when you start the job, not when payment is late.

Lien filing deadline in Tennessee

If the GC hired you, you have 90 days after completion of the project to record a mechanics lien in Tennessee, about the same as the national median of 90 days (counted from last furnishing on a sample job). 23 of the 51 jurisdictions we track use this same lien deadline, which makes it the most common rule.

90 days after completion or abandonment of the improvement.

Note what the clock counts from: completion of the project, not your own last day. A trade that finishes early may have more time than the number suggests, but the completion date is often unclear. The calculator uses your last furnishing date when you leave completion blank, which gives the earlier, safer date.

Deadline to sue on the lien

To keep the lien alive you must sue to enforce it within 90 days after recording the lien. If you record on the last possible day, that is about 180 days after your last day on the job, about 185 days shorter than the national median of 365 days. 2 of the 48 jurisdictions we track have a shorter overall time to sue and 42 have a longer one.

Because the clock counts from recording, recording early also moves the lawsuit deadline earlier.

General contractors: 12 months after recording the lien.

How Tennessee compares

Days are counted on a sample job with the lien recorded on its last allowed day, so states that count from recording or from completion can be compared with those that count from your last day on site. The median is across the jurisdictions with a dated rule on file.

Tennessee deadlines vs the national median
Record the lien (from last day)
Tennessee: 90 days
National median: 90 days
Sue to enforce (from last day)
Tennessee: 180 days
National median: 365 days

Public and federal projects

Public property can't be liened, so subcontractors and suppliers on state and local public jobs in Tennessee claim against the GC's payment bond instead. We haven't reduced Tennessee's bond claim deadlines to one set of numbers, because they vary by agency and project. The governing law is Tenn. Code §12-4-201 to -206. Verify the notice and suit deadlines with the statute and the bond itself before the job starts.

Federal jobs in Tennessee follow the Miller Act instead of state law: those hired by a sub or supplier give the prime contractor notice within 90 days of their last furnishing, and suit is due within 1 year, in federal court. Prime contractors on federal work have no lien or bond claim.

Retainage and prompt payment in Tennessee

On public work the cap is 5%, the most common cap among states that set one. Up to 5%, deposited in a separate interest-bearing escrow account.

Private work has a cap too: 5%. Up to 5% on projects over $500,000, held in escrow.

Retainage and prompt payment in Tennessee
Public workPrivate workFederal work
Retainage cap5%5%10%
ReleaseWithin 90 days after substantial completion.Within 90 days after substantial completion.Released with final payment, or earlier once progress is satisfactory.
GC pays subs withinVerifyVerify7 days
Late-payment interestVerifyVerifyTreasury prompt payment rate (reset every January and July)

Not legal advice. Retainage and prompt payment rules differ by agency, contract size and contract date, and change often. Confirm the rules with the current statute, your contract and a construction attorney before relying on them.

Worked example: a framing sub in Tennessee

A framing subcontractor hired by the GC on a private medical office building in Tennessee starts work on March 2, 2026 and last furnishes on July 17, 2026. The project is completed on August 28, 2026. Run through Tennessee's rules, those dates give:

Deadlines for the worked example in Tennessee
DeadlineDateCounted from
Notice of nonpayment: March 2026 work June 29, 2026 Verify First furnishing
Notice of nonpayment: April 2026 work July 29, 2026 Verify First furnishing
Notice of nonpayment: July 2026 work October 29, 2026 Verify First furnishing
Record the lien November 26, 2026 Project completion
Sue to enforce the lien February 24, 2027 Verify Lien recording

The first deadline on the calendar is “Notice of nonpayment: March 2026 work” on June 29, 2026, counted from the day the crew started, long before any payment is late.

2 more monthly notice dates fall between the rows shown; the calculator lists every one.

Rows marked "Verify" depend on facts or readings we can't settle for you. Check them against Tenn. Code §66-11-101 to -208.

Because Tennessee counts from project completion (August 28), not the sub's last day (July 17), the lien deadline is later than a last-furnishing state would give.

Open the lien deadline calculator for Tennessee and enter your own dates to get this table for your job, with countdowns and a PDF deadline calendar.

Check your own dates with the free tools

Statutes cited

  • Tenn. Code §66-11-101 to -208
  • Tenn. Code §12-4-201 to -206 (public bonds)
  • Tenn. Code §66-34-101 to -704 (Prompt Pay Act)
  • Federal work in Tennessee: 40 U.S.C. §3131 to §3134 (Miller Act)

Not legal advice. Lien and bond claim rules change and have exceptions for project type, contract terms and how notices are served. Confirm every deadline with the current statute or a construction attorney in the project's state before relying on it. Rules shown as "Verify with state statute" have exceptions or variations we could not reduce to one number.

Tennessee lien and payment FAQs

How long do I have to file a mechanics lien in Tennessee?

If you're a subcontractor or supplier hired by the GC, you have 90 days after completion of the project. 90 days after completion or abandonment of the improvement. Check the exact date for your job with the free lien deadline calculator, and confirm it with the statute (Tenn. Code §66-11-101 to -208).

Is a preliminary notice required in Tennessee?

Subcontractors and suppliers give a notice of nonpayment within 90 days after the last day of each month you furnish. It is required only in some cases. Remote contractors (no contract with the owner): within 90 days after the last day of each month with unpaid work.

How long is a mechanics lien valid in Tennessee?

Unless you sue to enforce it within 90 days after recording the lien, the lien expires.

What is the maximum retainage in Tennessee?

Up to 5% on public work (Up to 5%, deposited in a separate interest-bearing escrow account). Up to 5% on private work (Up to 5% on projects over $500,000, held in escrow).

How fast must a general contractor pay subcontractors in Tennessee?

We don't have one prompt payment number on file for Tennessee; timing depends on the contract and the agency. Verify with Tenn. Code §66-34-101 to -704 (Prompt Pay Act).

Can I file a lien on a public project in Tennessee?

No. Public property can't be liened, so subs and suppliers claim against the GC's payment bond under Tennessee's public bond law (Tenn. Code §12-4-201 to -206). Its deadlines vary by agency, so verify them before the job starts.

Neighboring states

Working across the state line? Rules change at the border, even on the same kind of job.

Same lien deadline (90 days): California , District of Columbia , Utah .