Skip to content
Profound Estimates

State guide

District of Columbia mechanics lien and payment rules

As a subcontractor in the District of Columbia, you have 90 days after completion of the project to record a mechanics lien. Here are the District's notice, lien, bond claim, retainage and prompt payment rules in plain language, with the statutes and a worked example.

  • Reviewed
  • 3 statutes cited
  • Not legal advice

District of Columbia at a glance

Private commercial work, sub hired by the GC, unless noted
Preliminary notice (subs)
No general preliminary notice
Record the lien (subs)
90 days after completion of the project
Sue to enforce
180 days after recording the lien
Public retainage cap
Verify with state statute
Private retainage cap
Verify with state statute
GC pays subs within
Verify with state statute

Turn these rules into dates for your job, free in your browser.

Preliminary notices in the District of Columbia

The District of Columbia is one of the states with no general preliminary notice for subcontractors on commercial work in our summary. That doesn't mean you can skip paperwork: the lien itself still has a hard deadline, and the other notices below still apply.

Lien filing deadline in the District of Columbia

If the GC hired you, you have 90 days after completion of the project to record a mechanics lien in the District of Columbia, about the same as the national median of 90 days (counted from last furnishing on a sample job). 23 of the 51 jurisdictions we track use this same lien deadline, which makes it the most common rule.

Any time during construction or within 90 days after the building or improvement is complete.

Note what the clock counts from: completion of the project, not your own last day. A trade that finishes early may have more time than the number suggests, but the completion date is often unclear. The calculator uses your last furnishing date when you leave completion blank, which gives the earlier, safer date.

Recording isn't the last step. Subcontractors and suppliers then serve notice of the lien on the owner (verify the timing with the statute).

Deadline to sue on the lien

To keep the lien alive you must sue to enforce it within 180 days after recording the lien. If you record on the last possible day, that is about 270 days after your last day on the job, about 95 days shorter than the national median of 365 days. 11 of the 48 jurisdictions we track have a shorter overall time to sue and 34 have a longer one.

Because the clock counts from recording, recording early also moves the lawsuit deadline earlier.

How DC compares

Days are counted on a sample job with the lien recorded on its last allowed day, so states that count from recording or from completion can be compared with those that count from your last day on site. The median is across the jurisdictions with a dated rule on file.

District of Columbia deadlines vs the national median
Record the lien (from last day)
District of Columbia: 90 days
National median: 90 days
Sue to enforce (from last day)
District of Columbia: 270 days
National median: 365 days

Public and federal projects

Public property can't be liened, so subcontractors and suppliers on state and local public jobs in the District of Columbia claim against the GC's payment bond instead. We haven't reduced the District's bond claim deadlines to one set of numbers, because they vary by agency and project. The governing law is D.C. Code §2-201.01. Verify the notice and suit deadlines with the statute and the bond itself before the job starts.

Federal jobs in the District of Columbia follow the Miller Act instead of state law: those hired by a sub or supplier give the prime contractor notice within 90 days of their last furnishing, and suit is due within 1 year, in federal court. Prime contractors on federal work have no lien or bond claim.

Retainage and prompt payment in the District of Columbia

We haven't reduced the District's retainage and prompt payment rules to single numbers yet: they depend on the agency, the contract size or the contract date. Rather than guess, the table shows "Verify" and the statutes to read are D.C. Code §2-221.01 to .06 (prompt pay). Your contract's payment terms still matter, and the federal rules below apply on federal work.

Retainage and prompt payment in the District of Columbia
Public workPrivate workFederal work
Retainage capVerifyVerify10%
ReleaseVerify with state statuteVerify with state statuteReleased with final payment, or earlier once progress is satisfactory.
GC pays subs withinVerifyVerify7 days
Late-payment interestVerifyVerifyTreasury prompt payment rate (reset every January and July)

Not legal advice. Retainage and prompt payment rules differ by agency, contract size and contract date, and change often. Confirm the rules with the current statute, your contract and a construction attorney before relying on them.

Worked example: a masonry sub in the District of Columbia

A masonry subcontractor hired by the GC on a private distribution warehouse in the District of Columbia starts work on March 2, 2026 and last furnishes on July 17, 2026. The project is completed on August 28, 2026. Run through the District's rules, those dates give:

Deadlines for the worked example in the District of Columbia
DeadlineDateCounted from
Record the lien November 26, 2026 Project completion
Sue to enforce the lien May 25, 2027 Lien recording
Serve notice of the lien on the owner Verify with state statute No single date

The first deadline on the calendar is “Record the lien” on November 26, 2026.

Rows marked "Verify" depend on facts or readings we can't settle for you, and rows without a date have no single number in the statute. Check them against D.C. Code §40-301.01 to -303.20.

Because the District of Columbia counts from project completion (August 28), not the sub's last day (July 17), the lien deadline is later than a last-furnishing state would give.

Open the lien deadline calculator for DC and enter your own dates to get this table for your job, with countdowns and a PDF deadline calendar.

Check your own dates with the free tools

Statutes cited

  • D.C. Code §40-301.01 to -303.20
  • D.C. Code §2-201.01 (public bonds)
  • D.C. Code §2-221.01 to .06 (prompt pay)
  • Federal work in the District: 40 U.S.C. §3131 to §3134 (Miller Act)

Not legal advice. Lien and bond claim rules change and have exceptions for project type, contract terms and how notices are served. Confirm every deadline with the current statute or a construction attorney in the project's state before relying on it. Rules shown as "Verify with state statute" have exceptions or variations we could not reduce to one number.

District of Columbia lien and payment FAQs

How long do I have to file a mechanics lien in the District of Columbia?

If you're a subcontractor or supplier hired by the GC, you have 90 days after completion of the project. Any time during construction or within 90 days after the building or improvement is complete. Check the exact date for your job with the free lien deadline calculator, and confirm it with the statute (D.C. Code §40-301.01 to -303.20).

Is a preliminary notice required in the District of Columbia?

Our summary of the District's statute has no general preliminary notice for subcontractors on commercial work. Residential projects and specific project types can differ, so confirm with the statute.

How long is a mechanics lien valid in the District of Columbia?

Unless you sue to enforce it within 180 days after recording the lien, the lien expires.

What is the maximum retainage in the District of Columbia?

We haven't reduced the District's retainage rules to one number; they depend on the agency, contract size or contract date. Verify with D.C. Code §2-221.01 to .06 (prompt pay).

How fast must a general contractor pay subcontractors in the District of Columbia?

We don't have one prompt payment number on file for the District of Columbia; timing depends on the contract and the agency. Verify with D.C. Code §2-221.01 to .06 (prompt pay).

Can I file a lien on a public project in the District of Columbia?

No. Public property can't be liened, so subs and suppliers claim against the GC's payment bond under the District's public bond law (D.C. Code §2-201.01). Its deadlines vary by agency, so verify them before the job starts.

Neighboring states

Working across the state line? Rules change at the border, even on the same kind of job.

Same lien deadline (90 days): California , Tennessee , Utah .