Trade guide · CSI 26 00 00

How to estimate electrical

Electrical estimates are built from counts (devices, fixtures, equipment connections) and lengths (conduit, wire, feeders), priced with labor units for each item. Most of the cost is labor, so production assumptions matter more than material waste.

Main unit
each
Typical production
320 LF/crew-day
Waste
5 to 10%
Labor
5.0 hrs per 100 LF

Typical planning figures from our production and takeoff data (emt conduit 3/4 in, with supports), not a promise of output or a price. Reviewed September 28, 2026.

Units of measure for electrical

Each piece of electrical work has its own unit, and keeping them apart is what makes the estimate checkable. These are the units estimators use and how each is measured.

Electrical units of measure
ItemUnitHow it's measured
DeviceseachReceptacles, switches and data boxes counted by type from the power and lighting plans.
Light fixtureseachCounted by fixture type from the fixture schedule.
Branch conduitLFMeasured home run and circuit routing, by size and type; often estimated per device on fit-outs.
WireLFConduit length × conductors per run, plus tails at boxes and panels.
FeedersLFMeasured from the single-line diagram and riser, by size.
Gear and equipmenteachPanels, transformers, disconnects and equipment connections.

How estimators take off electrical

  1. Count devices and fixtures. Count by type on each plan, color-coding as you go. These counts drive most of the labor.
  2. Measure feeders from the single line. Take each feeder's route and length, with conductor size and count.
  3. Measure or allow branch circuiting. Measure conduit on detailed jobs; on repetitive fit-outs, estimators often use a length per device from past jobs.
  4. Add wire, fittings and supports. Wire is conduit length times conductors plus tails. Fittings, straps and supports are typically an allowance on the conduit.
  5. Apply labor units or crew production. Price labor per unit (hours per device, per 100 ft of conduit) and adjust for height, access and occupied work.

Waste factors and order quantities

Waste covers cut-offs, breakage, laps and spillage, and it's added to the net quantity before rounding up to what the supplier sells. These are typical planning figures; your own job history is the better number.

Electrical waste factors
ItemFactorNotes
Wire5 to 10%Typical planning figure for tails, pulls and cut-offs.
Conduit5 to 10%Typical planning figure for offsets and cut-offs; fittings priced separately.

Crew production rates

Labor is quantity divided by production. These rates are per 8-hour crew-day for commercial work, from the same library as the crew-day production estimator: typical mid-range planning values with a low-to-high range, not a promise of output. Crew skill, layout, access and weather move them, and your own crews' records beat any library.

Electrical crew production per crew-day
ActivityCrewLowTypicalHighLabor
EMT conduit 3/4 in, with supports 2 electricians 250 320 LF 400 5.0 hrs per 100 LF
Pull #12 THHN wire 2 electricians 2,000 2,500 LF 3,200 0.6 hrs per 100 LF
Install and trim devices 2 electricians 40 55 each 70 0.29 hrs per each
2x4 LED troffers in grid ceiling 2 electricians 20 28 each 35 0.57 hrs per each
Production range per crew-day
EMT conduit 3/4 in, with supports 250 to 400 LF, typical 320
Pull #12 THHN wire 2,000 to 3,200 LF, typical 2,500
Install and trim devices 40 to 70 each, typical 55
2x4 LED troffers in grid ceiling 20 to 35 each, typical 28

Worked example: 600 devices on a tenant fit-out

The activity is install and trim devices, with a crew of 2 electricians at the typical rate of 55 each per crew-day:

  • Crew-days: 600 each ÷ 55 = 10.9 crew-days.
  • Labor hours: 10.9 crew-days × 2 workers × 8 hours = 175 hours.
  • Range: 8.6 crew-days at the high rate to 15 at the low rate, a spread of 6.4 crew-days on the same quantity.

Multiply the labor hours by your burdened hourly cost to price the labor. The spread between the low and high rate is why production is the assumption to check first on a electrical bid: the same takeoff can carry very different labor. Run your own quantities in the crew-day production estimator, and get the burdened rate from the labor burden calculator.

What drives the cost

  • Labor productivity. Height, ceiling access, occupied spaces and phasing change labor far more than material.
  • Wiring method. EMT, MC cable and rigid conduit have very different labor per foot.
  • Gear lead times. Switchgear and transformer pricing and lead times can move a bid; quotes should state validity.
  • Low voltage and controls. Fire alarm, data and controls are often separate scopes and need to be clearly in or out.

Common exclusions and clarifications

A electrical price is only as good as the scope it describes. These exclusions come from our scope library for electrical (CSI 26 00 00); list the ones that apply so the GC levels your number fairly.

  • Utility company charges, transformer pads and primary service work.
  • Low-voltage, data, security, audio-visual and fire alarm systems unless listed as included.
  • Control wiring for mechanical equipment.
  • Trenching, backfill and concrete encasement in rock or unsuitable soils.
  • Temporary power beyond one service drop.
  • Light fixtures not listed on the fixture schedule or furnished by the owner.

Clarifications that often go with them:

  • Fixture quantities per the fixture schedule; substitutions priced on request.
  • Temporary power limited to one service drop.

Pick, edit and export these in the scope inclusions and exclusions library, or load them straight into a proposal with the bid proposal builder.

Free tools for electrical estimating

Electrical estimating FAQs

How do electrical estimators price labor?

With labor units: hours per device, per fixture or per 100 feet of conduit and wire, adjusted for conditions. The crew production tool shows the same idea as units per crew-day (for example, devices installed and trimmed per day).

How much waste for wire and conduit?

As a typical planning figure, 5 to 10% on wire and conduit. Wire length should already include tails at boxes and panels before waste is added.

What should an electrical proposal exclude?

Common exclusions include utility company charges, low-voltage and fire alarm systems, control wiring for mechanical equipment and arc-flash studies unless included. The scope library lists proposal-ready wording.