Skip to content
Profound Estimates

Trade guide · CSI 31 00 00

How to estimate sitework

Sitework is priced mostly by equipment production: cubic yards of cut and fill, linear feet of trench, square yards of base and paving. Getting volumes right means keeping bank, loose and compacted yards straight.

Main unit
CY
Typical production
600 CY/crew-day
Waste
20 to 30%
Labor
2.7 hrs per 100 CY

Typical planning figures from our production and takeoff data (bulk excavation, load trucks), not a promise of output or a price. Reviewed September 28, 2026.

Units of measure for sitework

Each piece of sitework work has its own unit, and keeping them apart is what makes the estimate checkable. These are the units estimators use and how each is measured.

Sitework and Earthwork units of measure
ItemUnitHow it's measured
Excavation and fillCYCut and fill volumes from existing and proposed grades, by grid or cross-section.
TrenchingLFUtility runs by depth and width, with bedding and backfill.
Aggregate baseSY or tonsArea × thickness, converted to tons where the supplier sells by weight.
Asphalt pavingSY or tonsArea by lift thickness, converted to tons.
HaulCY loose or loadsExcavated volume × swell, ÷ truck capacity.
Erosion controlLF / eachSilt fence, inlet protection and construction entrances.

How estimators take off sitework

  1. Compute cut and fill. Compare existing and proposed surfaces by grid or cross-section to get bank cubic yards of cut and compacted yards of fill.
  2. Balance the site. Apply swell and shrink to see what must be imported or exported.
  3. Measure utilities and paving. Trench LF by depth; base and paving by area and thickness.
  4. Match equipment to quantities. Pick the fleet and use production per crew-day to get equipment days.
  5. Add trucking, dewatering and testing. Haul distance, dump fees, dewatering, compaction testing and erosion control are separate lines.

Waste factors and order quantities

Waste covers cut-offs, breakage, laps and spillage, and it's added to the net quantity before rounding up to what the supplier sells. These are typical planning figures; your own job history is the better number.

Sitework and Earthwork waste factors
ItemFactorNotes
Swell (common earth)20 to 30%Typical planning figure for bank to loose volume when hauling.
Shrink (compacted fill)10 to 20%Typical planning figure for bank to compacted volume; soils vary widely.

Crew production rates

Labor is quantity divided by production. These rates are per 8-hour crew-day for commercial work, from the same library as the crew-day production estimator: typical mid-range planning values with a low-to-high range, not a promise of output. Crew skill, layout, access and weather move them, and your own crews' records beat any library.

Sitework and Earthwork crew production per crew-day
ActivityCrewLowTypicalHighLabor
Bulk excavation, load trucks 1 operator, 1 laborer 400 600 CY 900 2.7 hrs per 100 CY
Utility trench, 4 ft deep, backfill 1 operator, 2 laborers 150 220 LF 320 10.9 hrs per 100 LF
Aggregate base, spread and compact 6 in 1 operator, 2 laborers 600 900 SY 1,300 2.7 hrs per 100 SY
Asphalt paving, 2 in lift Paving crew of 6 1,500 2,200 SY 3,000 2.2 hrs per 100 SY
Production range per crew-day
Bulk excavation, load trucks 400 to 900 CY, typical 600
Utility trench, 4 ft deep, backfill 150 to 320 LF, typical 220
Aggregate base, spread and compact 6 in 600 to 1,300 SY, typical 900
Asphalt paving, 2 in lift 1,500 to 3,000 SY, typical 2,200

Worked example: 15,000 CY of bulk excavation loaded to trucks

The activity is bulk excavation, load trucks, with a crew of 1 operator, 1 laborer at the typical rate of 600 CY per crew-day:

  • Crew-days: 15,000 CY ÷ 600 = 25 crew-days.
  • Labor hours: 25 crew-days × 2 workers × 8 hours = 400 hours.
  • Range: 16.7 crew-days at the high rate to 37.5 at the low rate, a spread of 20.8 crew-days on the same quantity.
  • Equipment: Excavator (30 to 40 ton), about 25 equipment-days.

Multiply the labor hours by your burdened hourly cost to price the labor. The spread between the low and high rate is why production is the assumption to check first on a sitework bid: the same takeoff can carry very different labor. Run your own quantities in the crew-day production estimator, and get the burdened rate from the labor burden calculator.

What drives the cost

  • Soil conditions. Rock, water and unsuitable soils are the biggest risks; state what's assumed.
  • Haul distance. Truck cycle times and dump fees can outweigh the excavation itself.
  • Equipment fleet. Matching machines to quantities decides production; owning versus renting changes the hourly cost.
  • Weather. Wet seasons stop earthwork and can require drying or replacing soils.

Common exclusions and clarifications

A sitework price is only as good as the scope it describes. These exclusions come from our scope library for sitework and excavation (CSI 31 00 00); list the ones that apply so the GC levels your number fairly.

  • Rock excavation, blasting and removal of unsuitable soils.
  • Import or export of material beyond the quantities stated.
  • Dewatering.
  • Survey and layout.
  • Testing and inspection.
  • Erosion control maintenance after substantial completion of our work.

Clarifications that often go with them:

  • Quantities based on the grading plan; import or export beyond the stated quantities is extra.
  • Rock and unsuitable soils excluded unless listed.

Pick, edit and export these in the scope inclusions and exclusions library, or load them straight into a proposal with the bid proposal builder.

Free tools for sitework estimating

Sitework and Earthwork estimating FAQs

What's the difference between bank, loose and compacted cubic yards?

Bank yards are soil in place. Excavated soil swells into more loose yards (roughly 20 to 30% for common earth as a typical planning figure), and compacted fill takes up fewer yards than it did in the bank. Haul is priced on loose yards; fill on compacted.

How is excavation production estimated?

By equipment and crew per day. Our crew production library uses a typical 600 CY per day for a 30 to 40 ton excavator loading trucks, with a range of 400 to 900. Truck count and haul distance often limit it.

What do sitework proposals usually exclude?

Rock excavation and blasting, unsuitable soil removal, import or export beyond stated quantities, dewatering, survey and layout, and testing, unless included.

Short on time for the sitework takeoff?

We calculate cut and fill, trenching and paving quantities from your grading and utility plans, and price the site scope.

Learn about the service