How to estimate roofing

Roofing is measured in squares (100 SF of roof surface), corrected for pitch on sloped roofs, with ridges, eaves, rakes, flashings and penetrations taken off by length or count. Low-slope membrane and steep-slope shingle roofs share the unit but little else.

Main unit
SQ (100 SF)
Typical production
35 SQ/crew-day
Waste
10%
Labor
1.14 hrs per SQ

Typical planning figures from our production and takeoff data (tpo membrane, mechanically attached, with insulation), not a promise of output or a price. Reviewed September 28, 2026.

Units of measure for roofing

Each piece of roofing work has its own unit, and keeping them apart is what makes the estimate checkable. These are the units estimators use and how each is measured.

Roofing units of measure
ItemUnitHow it's measured
Roof surfaceSQ (100 SF)Plan area × pitch factor on sloped roofs; plan area on low-slope roofs.
ShinglesbundlesSquares with waste × 3 bundles per square (tool default).
UnderlaymentrollsRoof SF plus 10% laps ÷ roll coverage.
Ridge, hip, eave, rakeLFMeasured on plan (rakes corrected for slope) for starter, ridge cap and drip edge.
Membrane, insulation, cover boardSQLow-slope field area, plus base flashing up walls and curbs.
Penetrations and curbseachCounted from the roof plan for flashing.

How estimators take off roofing

  1. Measure each roof plane. Take plan dimensions including overhangs for each plane or roof area, and note its pitch.
  2. Correct for pitch. Multiply plan area by the pitch factor, √(rise² + 12²) ÷ 12. A 6/12 roof is 1.118 times its plan area.
  3. Take off edges and details. Eaves, rakes, ridges, hips, valleys, walls and penetrations drive starter, ridge cap, flashing and edge metal.
  4. Add waste and convert. Add 10% waste (tool default; more on cut-up roofs), then convert squares to bundles, rolls and pieces.
  5. Price labor and equipment. Use squares per crew-day for the system and add hoisting, tear-off, disposal and safety equipment.

Waste factors and order quantities

Waste covers cut-offs, breakage, laps and spillage, and it's added to the net quantity before rounding up to what the supplier sells. Figures marked as tool defaults are the same ones the Trade Takeoff Worksheets start with, and you can edit them there.

Roofing waste factors
ItemFactorNotes
Shingles and membrane10%Tool default; hips, valleys and dormers push it higher.
Underlayment laps10%Tool default.
Ice and water shield3 ft up from eavesTool default; follow local code.

Crew production rates

Labor is quantity divided by production. These rates are per 8-hour crew-day for commercial work, from the same library as the crew-day production estimator: typical mid-range planning values with a low-to-high range, not a promise of output. Crew skill, layout, access and weather move them, and your own crews' records beat any library.

Roofing crew production per crew-day
ActivityCrewLowTypicalHighLabor
TPO membrane, mechanically attached, with insulation 5 roofers 25 35 SQ 45 1.14 hrs per SQ
Architectural asphalt shingles 4 roofers 18 25 SQ 32 1.28 hrs per SQ
Production range per crew-day
TPO membrane, mechanically attached, with insulation 25 to 45 SQ, typical 35
Architectural asphalt shingles 18 to 32 SQ, typical 25

Worked example: a 40,000 SF (400 square) TPO roof

The activity is tpo membrane, mechanically attached, with insulation, with a crew of 5 roofers at the typical rate of 35 SQ per crew-day:

  • Crew-days: 400 SQ ÷ 35 = 11.4 crew-days.
  • Labor hours: 11.4 crew-days × 5 workers × 8 hours = 457 hours.
  • Range: 8.9 crew-days at the high rate to 16 at the low rate, a spread of 7.1 crew-days on the same quantity.
  • Equipment: Material hoist or telehandler, about 11.4 equipment-days.

Multiply the labor hours by your burdened hourly cost to price the labor. The spread between the low and high rate is why production is the assumption to check first on a roofing bid: the same takeoff can carry very different labor. Run your own quantities in the crew-day production estimator, and get the burdened rate from the labor burden calculator.

What drives the cost

  • Tear-off. Removing existing layers, disposal and deck repair are often the biggest unknowns.
  • Pitch and height. Steep and tall roofs need more safety equipment and cut production.
  • Details. Penetrations, curbs, walls and complex edges take more time than field membrane.
  • Warranty. Longer manufacturer warranties require specific systems and inspections.

Common exclusions and clarifications

A roofing price is only as good as the scope it describes. These exclusions come from our scope library for roofing (CSI 07 50 00); list the ones that apply so the GC levels your number fairly.

  • Tear-off of more than one existing layer, or replacement of rotted decking beyond the allowance.
  • Structural deck repair.
  • Roof hatches, curbs and equipment supports furnished by others.
  • Flashing of penetrations installed after the roof is complete.
  • Roof walkway pads unless listed as included.
  • Lightning protection.

Clarifications that often go with them:

  • Flashing of penetrations installed before the roof; later penetrations flashed at time and material.
  • One layer of existing roofing removed where tear-off is included.

Pick, edit and export these in the scope inclusions and exclusions library, or load them straight into a proposal with the bid proposal builder.

Free tools for roofing estimating

Roofing estimating FAQs

How many bundles of shingles are in a square?

Most architectural shingles are three bundles per square (100 SF), which is the takeoff tool's default. Check the manufacturer's coverage for the product you're using.

How do I account for roof pitch?

Multiply the plan area by the pitch factor, √(rise² + 12²) ÷ 12. For example, a 4/12 roof is 1.054 times its plan area, a 6/12 roof 1.118 and an 8/12 roof 1.202.

What waste factor should I use for roofing?

The takeoff tool defaults to 10% for a simple gable roof. Roofs with many hips, valleys and dormers need more; as a typical planning figure, 12 to 15%.